| 1 | Earthwork in excavation of foundation of structures of culverts, abutments piers, retaining walls etc. as per drawing and technical specification, in all types of strata comprising any of the material such as soil, silt sand, clay, gravel, murrum of all varieties shingles, pebbles all types of conglomerates, laterite rock etc soft rock, ordinary rock or disintegrated rock fissured shattered/decomposed rock or weathered rock all such material as described under appendix to those specification either in full or in parts as the case may be adopting mechanical means (hydraulic excavator) or any approved method or methods as the case may be convenient or permitted inclusive of chiseling and wedging etc in all conditions such as dry, moist, saturated, submerged, foul condition etc including setting out, construction of shoringand bracing, removal of stumps and other deleterious matter, dressing sides, ramming of bottoms, getting out the excavated soil/rock to be leveled and neatly dressed, pumping and bailing out of water, back filling the excavated earth to the extent required and utilizing the remaining earth locally for road work, barricading, danger lightening, guarding and disposal of excavated earth as directed by the engineer in charge all complete including all leads and lifts and up to depth of excavation as per MORTH Specification 304 | 117.00 | M3 |
| 2 | Earthwork in excavation of foundation of structures of culverts, abutments piers, retaining walls etc. as per drawing and technical specification, in all types of strata comprising any of the material such as soil, silt sand, clay, gravel, murrum of all varieties shingles, pebbles all types of conglomerates, laterite rock etc soft rock, ordinary rock or disintegrated rock fissured shattered/decomposed rock or weathered rock all such material as described under appendix to those specification either in full or in parts as the case may be adopting mechanical means (hydraulic excavator) or any approved method or methods as the case may be convenient or permitted inclusive of chiseling and wedging etc in all conditions such as dry, moist, saturated, submerged, foul condition etc including setting out, construction of shoringand bracing, removal of stumps and other deleterious matter, dressing sides, ramming of bottoms, getting out the excavated soil/rock to be leveled and neatly dressed, pumping and bailing out of water, back filling the excavated earth to the extent required and utilizing the remaining earth locally for road work, barricading, danger lightening, guarding and disposal of excavated earth as directed by the engineer in charge all complete including all leads and lifts and up to depth of excavation as per MORTH Specification 304 | 78.00 | m3 |
| 3 | Transportation and Carriage of Materials (A) By tipper truck including loading, unloading and stacking ( ii ) Earth | 156.00 | cum |
| 4 | Rubble packing with hard laterite stone under floors including watering ramming and consolidating etc. in pipeline trenches and other foundations complete.
| 30.00 | cum |
| 5 | Providing and laying in position cement concrete 1:2:4 (1 cement : 2 coarse sand: 4 graded granitic or basaltic stone aggregate 40 m nominal size) excluding cost of centering shuttering and finishing :>All works upto plinth level | 90.00 | cum |