| 1 | Excavation in soil in hilly areas in all heights and depths, in all kinds of soil including saturated soil comprising of mixed soil, ordinary rock and hard rock. All work of rock cutting by blasting shall be carried out by taking all necessary precautions against soil erosion, damages to hill side, water pollution etc. and to protect stability of hill side. Rock shall be excavated with chiseling and wedging out of rock (where blasting is prohibited). All earth work in cutting/excavation including rock excavation shall be carried out true to lines, grades, side slopes, width, camber, super-elevation and level as shown on the drawing and as directed by the Engineer-in-Charge in conformity with the requirement of MoRD technical specification for Rural Road, Section. 300 & 1600 to achieve designed formation width including hauling and stacking of materials useful for construction at suitable sites safe manner and disposal of all surplus material to the approved dumping sites through all modes of transportation including head load and animal transport and mechanical means along with its leveling, fine dressing and carriage of machineries, tools, equipment s and safety measures and other incidentals necessary to complete the work by mechanical means and labour if required. During the mobilization period, contractor should take the advanced x-sec in 15 m (fifteen metre) interval of whole road length in the presence of Engineer-in-charge or his representative. In case the advanced x-section has been taken in the presence of Engineer-in-Charge representative, in that case the same has to be got approved from Engineer-in-Charge. The land for dumping sites shall be arranged by the contractors himself and nothing extra shall be paid on this account, filling of unevenness blind age and finishing of the road to specified dimensions or as directed by the Engineer-in-charge for smooth riding. The recovery for stones, whether useful or 288.98 (Two hundred Eighty Eight point Nine Eight) cubic metre at the rate of Rs 300/-only (Rupees three hundred only) per cubic meter amounting to Rs. 86,694.00 only shall be effected on prorata basis in all circumstances. Any loss to the public and private property during the course of excavation shall be the absolute responsibility of the contractor, which shall have to be duly compensated by him in all cases. The rate is including Octroi, Royality, Malkana, Toll Tax or any other Taxes imposed by the Government but excluding GST. | 7745.37 | Per cubic metre |
| 2 | Earth work in excavation for all type of road structure such as retaining walls, breast walls, culverts, drain and Parapets etcetra in all type of classification of soil comprising of ordinary soil, ordinary rock, hard rock chiseling/wedging out rocks (Where blasting is prohibited) as per drawings and MORD technical specification section 300 and 1600 and as per direction of the Engineer-in-Charge including setting out, construction of shoring and bracing, removal of stumps and other deleterious materials and disposal of materials upto any lead and lift including dressing of sides, bottom and back filling in trenches with excavated suitable approved material to the original surface in layer not executing 150 mm (one hundred fifty millimetre) compacted thickness including shoring and strutting and pumping and bailing out water (surface and sub soil water) upto any depth any quantum of water including cleaning of slush which may arise out during dewatering complete as per direction of Engineer- in-Charge. including carriage of materials within all leads, lifts and other incidentals. The rate is including Octroi, Royality, Malkana, Toll Tax or any other Taxes imposed by the Government but excluding GST. | 3197.40 | Per cubic metre |
| 3 | Construction of embankment with approved materials deposited at site from roadway cutting and excavation from drain and foundation of other structures graded and compacted to meet requirement of Tables 300.1 and 300.2 with all leads as per MORD Technical Specification section 300 complete and as per direction of Engineer-in-charge including carriage of materials within all leads, lifts and other incidentals. The rate is including Octroi, Royality, Malkana, Toll Tax or any other Taxes imposed by the Government but excluding GST. | 1184.40 | Per cubic metre |
| 4 | Providing and laying concrete mechanically mixed and vibrated 1:6:12 (one cement: Six sand: Twelve graded crushed stone aggregate 40mm (forty millimetre) nominal size) for plain/reinforced concrete in open foundation and plinths for similar works complete as per drawing and technical specification section 800, 900, 1200 & 1600 and curing complete including the cost of form work and hauling of material in all leads and lifts as per the entire satisfaction and direction of Engineer-in-charge. The rate is including Octroi, Royality, Malkana, Toll Tax or any other Taxes imposed by the Government but excluding GST. | 40.48 | Per cubic metre |
| 5 | Providing and laying concrete mechanically mixed and vibrated PCC M-10 1:3:6 (one cement: three sand: six graded crushed stone aggregate 20mm (twenty millimetre) nominal size) for plain/reinforced concrete in open foundation and plinths or similar works complete as per drawings and MoRD technical specification section 800, 900, 1200 & 1600 and curing complete including the cost of form work and hauling of material in all leads and lifts as per the entire satisfaction and direction of Engineer-in-charge. The rate is including Octroi, Royality, Malkana, Toll Tax or any other Taxes imposed by the Government but excluding GST. | 754.64 | Per cubic meter |