Complete Tender Details

Empowering Indian businesses in the procurement ecosystem since 2012

Tendering Authority: Military Engineer Services
Tender ID3477426
Organisation NameMilitary Engineer Services
Tender BriefCorrigendum : Construction Of Squad Post In Trg Area, Ground Preparation For Installation Of Inf Obst Course At Pms, Special Repair To Footpath From Stn Hq T Junction To Adm Area Of Flag House At Pms And Provn Of Arboriculture Works Near Officers Institute At Pms
Last Date For Submission24th Mar, 2026
Opening Date25 Mar, 2026
Cost
Document Cost500.00
EMD95500.00
Estimated Cost4773344.00
Location
CityPANAGARH
StateWest Bengal

Register to see full details

BOQ Items
#ItemQtyUnits
1Demolition of cement concrete (unreinforced) of any description and in any position not otherwise specifically provided for edging of footpath and removal of rubbish off the site complete all as specified and directed.22.00Cum
2Surface dressing n.exc 15 cm deep in soft / loose soil all as specified including clearing away all grass vegetation, saplings, shrubs, brush wood, under growth, roots and trees n. exc. 30cm girth and removing rubbish upto a distance of 50 metre out of the periphery of the area complete all as specified and as directed.248.00Sqm
3Excavating in trenches , n.exc 1.5 m wide and n.exc 1.5 m depth for foundation etc or for shafts, wells, cesspits ,manhole pier hole, laying of cables, pipes etc n.exc 10 sqm on plan and n.exc 1.5m in depth and getting out in any kind of soil Note : Manual excavation to be done. During excavation if any damage occured to existing cable any type/ water pipe line, it will be contractor responsibilty to get it repair and make functional by providing jointing kit etc without any extra cost. Contractor has to repair it within 24 hrs so that essential service can not be effected due to such damage.If contractor fails to repair it within 24 hrs penalty @ Rs 500/- will be charged to contractor. In this GE decision will be final, conclusive and binding. 100.00Cum
4Excavation over area n.exc 1.50m deep and getting out soft/loose soil complete all as spd and directed.111.00Cum
5Removing excavated material of soil n.exc 50m and depositing where directed at a level n.exc 1.50m above the starting point complete all as spd and directed.148.00Cum
24th Mar, 2026

6 Days Left