Complete Tender Details

Empowering Indian businesses in the procurement ecosystem since 2012

Tendering Authority: Public Works Department
Tender ID3799841
Organisation NamePublic Works Department
Tender BriefConstruction Of Dys-functional Toilets At Girls Primary School, Lehar Sathra Zone, Surankote Sub Div. Lassana Div. Surankote District Poonch. (under Samagra Shiksha 2025-26).
Last Date For Submission28th Mar, 2026
Opening Date30 Mar, 2026
Cost
Document Cost200.00
EMD1400.00
Estimated Cost70000.00
Location
CitySurankote
StateJammu and Kashmir

Register to see full details

BOQ Items
#ItemQtyUnits
1Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering. All works upto plinth level in (1:2:4) grade with 20mm nominal size of crushed stone aggre-gates.0.10Cum
2Providing and laying Ceramic glazed floor tiles 300x300 mm (thickness to be specified by the manufacturers) of 1st quality conforming to IS: 15622 of approved make, laid on 20 mm thick bed of cement mortar 1: 4 ( 1 cement : 4 coarse sand) including pointing the joints with white cement and matching pigment etc., complete. in colour such as White, Ivory, Grey, Fume Red Brown.2.23Sqm
3Providing and fixing Ist quality ceramic glazed wall tiles conforming to IS : 15622 (thickness to be specified by the manufacturer), of approved make, in all colours, shades except burgundy, bottle green, black of any size as approved by Engineer- in-Charge, in skirting, risers of steps and dados over 12 mm thick bed of cement mortar 1:3 ( 1 cement : 3 coarse sand) and jointing with grey cement slurry @ 3.3 kg per sqm, including pointing in white cement mixed with pigment of matching shade complete.21.32Sqm
4Making plinth protection 50mm thick with cement conc .(1:3:6) ,20 mm nominal size of stone aggregates over 75mm bed of dry brick ballast,40mm nominal size of well rammed and consolidated and grouted with fine sand including finishing the top smooth.2.78Sqm
5Finishing walls with water proofing cement paint of required shade New work (two or more coats) applied @ 3.84 kg/10 sqm .16.03Sqm
28th Mar, 2026