Complete Tender Details

Empowering Indian businesses in the procurement ecosystem since 2012

Tendering Authority: Kerala State Electricity Board
Tender ID3384433
Organisation NameKerala State Electricity Board
Tender BriefCorrigendum : Execution Of Metal Spreading And Development Of Safe Access Zone Around Rmu As Per Cea Safety Norms At Terls 110 Kv Substation
Last Date For Submission30th Mar, 2026
Opening Date06 Apr, 2026
Cost
Document Cost1630.00
EMD17240.00
Estimated Cost689521.00
Location
CityThiruvananthapuram
StateKerala

Register to see full details

BOQ Items
#ItemQtyUnits
12.28.1 : Surface dressing of the ground including removing vegetation and in equalities not exceeding 15 cm deep and disposal of rubbish, lead up to 50 m and lift up to 1.5 m.All kinds of soil294.000M2
22.8.1 : Earth work in excavation by mechanical means (Hydraulic excavator) /manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms, lift up to 1.5 m, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m.All kinds of soil25.000M3
32.25 : Filling available excavated earth (excluding rock) in trenches, plinth, sides of foundations etc. in layers not exceeding 20 cm in depth, cub.m 325.531 2 12 3906.37 CONTR consolidating each deposited layer by ramming and watering, lead up to 50 m and lift up to 1.5 m.Filling available excavated earth (excluding rock) in trenches, plinth, sides of foundation etc. in layers not exceeding 20 cm in depth, consolidating each deposited layer by ramming and watering, lead up to 50 m and lift up to 1.5 m.12.000M3
44.3.2 : Centering and shuttering including strutting, propping etc. and removal of form work for:Retaining walls, return walls, (any thickness) including attached pilasters, buttresses, plinth and string courses fillets, kerbs and steps etc.97.000M2
5Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:2:4 (cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size)26.500M3