Empowering Indian businesses in the procurement ecosystem since 2012
| Tender ID | 4560503 |
|---|---|
| Organisation Name | Military Engineer Services |
| Tender Brief | Corrigendum : Replacement Upgradation Of Old Transformer And Resuscitation Of Elect Panels And Associated Work Under Ge (u) Bathinda |
| Last Date For Submission | 7th Jul, 2026 |
| Opening Date | 09 Jul, 2026 |
| Document Cost | 3000.00 |
|---|---|
| EMD | 698500.00 |
| Estimated Cost | 74700000.00 |
| City | Bathinda |
|---|---|
| State | Punjab |
| # | Item | Qty | Units |
|---|---|---|---|
| 1 | Supply, installation, testing & commissioning of package type/unitised 11kV / 433 V Outdoor sub-station, 500kVA made from G. I. enclosure complete as required conforming to IEC 62271-202 and relevant IS/IEC specifications as applicable for the rating, Internal Arc of 21 KA/1 Sec. IAC AB on 1:2:4 (1 cement :2 cores and : 4 Graded stone aggrregate of 40 mm nominal size) PCC foundation of suitable size extending 500 mm all around the outdoor enclosure and 1000 mm height (above ground level) complete with suitable sizes of GI Pipes for incoming/outgoing cables/earthing strips etc. and consisting of following complete as required. Angle iron frame of size 40x40x5mm NS all along the corner of the foundation.Vacuum Interrupter, RMU, LT switchgear and CSS enclosure shall be of same make to ensure life cycle optimization. Note : Make of CSS -ABB,SEIMENS,SCHNEIDER. Package substation will have the following equipment :- | 2.00 | Each |
| 2 | A) HT SWITCHGEAR | ||
| 3 | 11kV 630Amps 21KA/3 sec. 3 Way Non-Extensible Ring Main Unit Compact switchgear consisting of 3 No. fixed motorised operated Vacuum Circuit Breaker Module in SF6 insulated stainless steel enclosure with copper busbar. Gas Tank shall be made out of SS 304 Grade with minimum 2.5 mm thick sheets Steel. HT RMU shall preferably have site replaceable bushings to have very less downtime in the event of bushing breakage and restoration can be done immediately without sending the RMU to OEM Works. The vacuum circuit breaker module should have independent fault-making type earthing switch and must not engage vacuum interrupter for earthing purpose of the cable. Interconnection between HT Switchgear and primary of transformer shall be done through 1C x 3R x 95 sq.mm Aluminium XLPE cable. - 1 No. | ||
| 4 | The RMU shall have following components: | ||
| 5 | INCOMING:- |
6 Days Left