| Tender ID | 4080591 |
|---|---|
| Organisation Name | Public Works Department |
| Tender Brief | Remodelling Of Pipe Drain Into Rcc Drain On Bhao Rao Devras Marg (from Pt. Deen Dyal Upadhyay Marg To Bg-7 Gate) Under Sub Division Nwr-24, Section-i, Division Nwr-2, During 2025-26. |
| Last Date For Submission | 29th Apr, 2026 |
| Opening Date | 29 Apr, 2026 |
| Document Cost | 0.00 |
|---|---|
| EMD | 152833.00 |
| Estimated Cost | 7641639.00 |
| City | Delhi |
|---|---|
| State | Delhi |
| # | Item | Qty | Units |
|---|---|---|---|
| 1 | Earth work in excavation by mechanical means (Hydraulic excavator) / manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms, for all lift, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m. All kinds of soil | 400.00 | Cum |
| 2 | Filling available excavated earth (excluding rock) in trenches, plinth, sides of foundations etc. in layers not exceeding 20cm in depth, consolidating each deposited layer by ramming and watering, lead up to 50 and for all lift. | 44.00 | Cum |
| 3 | Providing and laying in position ready mixed or site batched design mix cement concrete for plain cement concrete work; using coarse aggregate and fine aggregate derived from natural sources, Portland Pozzolana/Ordinary Portland /Portland Slag cement, admixtures in recommended proportions as per IS: 9103 to accelerate / retard setting of concrete, to improve durability and workability without impairing strength; including laying, curing, carriage for all leads; but excluding the cost of centering, shuttering and finishing as per direction of the engineer-in-charge; for the following grades of concrete. Note: In case the cement content in design mix is more than the minimum specified cement content, the contractor shall have discretion to either re-design the mix or bear the cost of extra cement. All works upto plinth level : Concrete of M10 grade with minimum cement content of 220 kg /cum | 94.00 | Cum |
| 4 | Providing and laying in position ready mixed or site batched design mix cement concrete for plain cement concrete work; using coarse aggregate and fine aggregate derived from natural sources, Portland Pozzolana/Ordinary Portland /Portland Slag cement, admixtures in recommended proportions as per IS: 9103 to accelerate / retard setting of concrete, to improve durability and workability without impairing strength; but excluding the cost of centering, shuttering and finishing as per direction of the engineer-in-charge; for the following grades of concrete. Note: In case the cement content in design mix is more than the minimum specified cement content, the contractor shall have discretion to either re-design the mix or bear the cost of extra cement. Concrete of M25 grade with minimum cement content of 300 kg /cum. | 38.00 | Cum |
| 5 | Centering and shuttering including strutting, propping etc. and removal of form for : (a )Foundations, footings, bases of columns, etc. for mass concrete | 112.00 | Sqm |