Complete Tender Details

Empowering Indian businesses in the procurement ecosystem since 2012

Tendering Authority: Municipal Administration And Water Supply Department
Tender ID4651605
Organisation NameMunicipal Administration And Water Supply Department
Tender BriefCorrigendum : Construction Of Additional Health Section Office Room Building At Zonal Office In Ward No-12.
Last Date For Submission7th Jul, 2026
Opening Date07 Jul, 2026
Cost
Document Cost0.00
EMD16200.00
Estimated Cost1620000.00
Location
CityErode
StateTamil Nadu

Register to see full details

BOQ Items
#ItemQtyUnits
1Removing the existing Doors and Windows including removal of frames, hinges and fastenings clearing away and carefully stacleing materials useful for reused for any thinlenes of wass etc., complete as per specification( W - 0029)7M2
2Labour charges for Refixing Door,Windows and ventilators along with frames in position etc., complete. ( W-0148)7M2
3Dismantling the existing damaged Brick work including dismantling clearing away and carefully stacleing materials useful for reused for any thinlenes of wass etc.,Complete as per standard specifications (W-0034)1.00225M3
4Earth work excavation for foundation in Hard stiff clay, stiff black cotton, hard red earth, shales murram, gravel, stoney earth and earth mixed with small size boulders SS.20B and Sand, silt or other loose soil, wet sand, silt not under water, light black cotton soil, sandy loam ordinary soil and to full depth as may be directed except in hardrock requiring blasting inclusive of shoring shuttering and baling out water wherever necessary refilling the sides of foundation with excavated soil other than sand in layers of 15cm thick well rammed and completed, cleaning and levelling the site etc.,complete - Narrow Foundations - Upto 2.00m Depth Footings"8.003775M3
5Plain Cement concrete 1:4:8 [one cement, four sand and eight course aggregates] using 40mm size Hard Broken/Machine crushed Granite Stone Jelly including dewatering if found necessary and laid in layers of not more than 15cm thick and compacted etc., complete complying with standard specification.7.00015M3
7th Jul, 2026