Empowering Indian businesses in the procurement ecosystem since 2012
| Tender ID | 3772949 |
|---|---|
| Organisation Name | Urban Development And Housing Department |
| Tender Brief | Corrigendum : Interior Renovation Works At Different Plants Of Gift City |
| Last Date For Submission | 7th Apr, 2026 |
| Opening Date | Refer to Documents |
| Document Cost | 5000.00 |
|---|---|
| EMD | 135000.00 |
| Estimated Cost | 6845000.00 |
| City | Gandhinagar |
|---|---|
| State | Gujarat |
| # | Item | Qty | Units |
|---|---|---|---|
| 1 | 1200016384: DISMANTLING OF EXISTING CIVIL ITEM: Dismantling of existing furniture /wall panelling /partition / ceiling /curtain /etc and disposal/stacking of dismantled items, including loading, unloading, transportation, all work shall be done as per the instructions of the engineer-in-charge. | 2.000 | LS |
| 2 | 1200016385: DISMANTLING OF EXISTING ELECTRIC ITEM: Dismantling of existing lighting fixture , wiring and disposal/stacking of dismantled items, including loading, unloading, transportation, all work shall be done as per the instructions of the Engineer-in-Charge. | 2.000 | LS |
| 3 | 1200016386: PandF POP PUNNING: Providing and fixing 6 to 12mm thick pop punning as per manufacturer's specification and all work shall be done as per the instructions of the Engineer-in-Charge. | 125.000 | M2 |
| 4 | 1200016441: PandL FLOORING VITRIFIED TILE: "Providing and laying flooring with 1200 mm x 600 mm Vitrified Tiles Make : Nitco or equivalent and sample in pattern as per detailed drawings on up to 35 mm to 45mm thick bed of cement sand mortar in a ratio of 1: 6, including surface preparation, applying neat cement float, giving necessary slopes, cleaning joints etc complete. Cost should be inclusive of cement screed in case the bedding thickness increases beyond 25 mm, it should also include the cost of hacking the existing IPS floor and all work shall be done as per the instructions of the Engineer-in-Charge." | 200.000 | M2 |
| 5 | 1200016387: PandL VITRIFIED TILE SKIRTING: Providing and laying Vitrified Tiles Skirting 75mm wide including surface preparation, applying neat cement float, giving necessary slopes, cleaning joints etc complete. Cost should be inclusive of cement screed in case the bedding thickness increases beyond 25 mm, it should also include the cost of hacking the existing IPS Floor and all work shall be done as per the instructions of the Engineer-in-Charge. | 25.000 | M |