Complete Tender Details

Empowering Indian businesses in the procurement ecosystem since 2012

Tendering Authority: Directorate General Of Lighthouses And Lightships
Tender ID4568492
Organisation NameDirectorate General Of Lighthouses And Lightships
Tender BriefCorrigendum : Replacement Of Trestle Tower At Agatti Lighthouse In The Ut Of Lakshadweep Transportation Erection Of Trestle Tower And Construction Of Service Room For Trestle Tower At Agatti Lh Site
Last Date For Submission14th Jul, 2026
Opening Date15 Jul, 2026
Cost
Document Cost0.00
EMD99997.00
Estimated Cost4999871.00
Location
CityGandhinagar
StateGujarat

Register to see full details

BOQ Items
#ItemQtyUnits
1Transportation of 30m high GI Trestle tower members from Deep Bhavan, Kochi to Agatti Lighthouse, Agatti Island, Lakshadweep including cost of all loading, unloading, transportation, ship /Manchu/barge rent charges, boat fare charges,tractor and hydra rent charge etc, stacking of materials at Agatti Lighthouse site and all other charges etc. complete as directed.8.90MT
2Providing and fixing double scaffolding system (cup lock type) on the exterior side, up to Tower height made with 40 mm dia M.S. tube 1.5 m centre to centre, horizontal & vertical tubes joining with cup & lock system with M.S. tubes, M.S. tube challies, M.S. clamps and M.S. staircase system in the scaffolding for working platform etc. and maintaining it in a serviceable condition for the required duration as approved and removing it there after .The scaffolding system shall be stiffened with bracings, runners, connection with the building etc wherever required for inspection of work at required locations with essential safety features for the workmen etc. complete as per directions and approval of Engineer in-charge .The elevational area of the scaffolding shall be measured for payment purpose .The payment will be made once irrespective of duration of scaffolding.768.00Sqm
3Dismantling doors, windows and clerestory windows (steel or wood) shutter including chowkhats, architrave, holdfasts etc. complete and stacking within 50 metres lead Including cost of all labour, tools and plants etc. complete as directed.1.00No.
4Dismantling existing damaged 30m high G.I. trestle tower carefully with out damaging the good members of the trestle tower and stacking materials carefully with numbering for transporting and use at other place where required including cost of labour, tools and plants, scaffolding charges etc. complete as directed.6,390.00Kg
5Demolishing R.C.C. work manually/ by mechanical means including stacking of steel bars and disposal of unserviceable material within 50 metres lead as per direction of Engineer - in- charge including cost of labour, tools and plants, scaffolding charges etc. complete as directed..60.00Cum
14th Jul, 2026

13 Days Left