Complete Tender Details

Empowering Indian businesses in the procurement ecosystem since 2012

Tendering Authority: Yamuna Expressway Industrial Development Authority
Tender ID4790619
Organisation NameYamuna Expressway Industrial Development Authority
Tender BriefCorrigendum : Construction Of Cc Road And Brick Drain In Village-karol Bangar, Yea. Wc-06
Last Date For Submission17th Jul, 2026
Opening Date21 Jul, 2026
Cost
Document Cost840.00
EMD34300.00
Estimated Cost1712174.00
Location
CityGautam Budnagar
StateUttar Pradesh

Register to see full details

BOQ Items
#ItemQtyUnits
1Earth work in excavation in ordinary in all of foundation tranches including dressing of side and ramming of bottom lifts upto a 1.5m including getting out the excavation soil and disposal of surplus excavated soil as directed with in a lead of 50m . AR24.5900Cum
2Cement concrete with 4cm Guage Approved Stone ballast , Coarse Sand& Cement in the proportion of 8:4:1 including Supply of all material, Labour, Tools & Plants etc required for Proper completion of the work. UPPWD/SOR/281/P-1773.7400Cum
3Providing and laying in position specified grade of reinforced cement concrete excluding the cost of centering, shuttering, finishing and reinforcement - All work up to plinth level: 1:1.5:3 (1 cement : 1.5 coarse sand : 3 graded stone aggregate 20 mm nominal size)UP PWD SOR 2020 /DAR-18/5.1.21.7300Cum
4Reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding all complete Thermo-Mechanically Treated bars.. UP PWD SOR 2020 /DAR-18/5.22.6170.0000Kg
5Construction of un-reinforced plain cement concrete pavement, thickness as per design, over a prepared sub base, with 43 grade cement or any other type as per Clause 1501.2.2 M 30(Grade) coarse and fine aggregates conforming to IS:383, maximum size of coarse aggregate not exceeding 25 mm,mixed a concrete mixer of not less than 0.2 cum capacity and appropriate weigh batcher using approved mix design, laid approved fixed side formwork (steel channel, laying and fixing of 125 micron thick polythene film, wedges, steel plates including levelling the formwork as per drawing), spreading the concrete with shovels, rakes, compacted using needie, screed and plate vibrators and| finished in continuous operation including provision of contraction and construction joints, applying debonding strips, primer, sealant near approaches to bridge/culvert and construction joints, admixtures as approved, curing of concrete slabs for 14 days,using curing compound (where specified) and water finishing to lines and grade as per drawing and finished with Power Trowel Cum Floter-Trimix Flooring Machine.Technical Specification Clause 1501. Including all taxes, material, T&P, Machinary. royalty, labour cess all taxes complete. Excluding GST as per E/l.29.6100Cum