Complete Tender Details

Empowering Indian businesses in the procurement ecosystem since 2012

Tendering Authority: Water Resources Department
Tender ID4938645
Organisation NameWater Resources Department
Tender BriefCorrigendum : Improvement To The Existing Nallah From Ghagreshwar Temple, To Prakash Kamat House, From Ch.24.00 Mts To Ch.58.00 Mts At Sinquerim In Ward No.i, Candolim In Calangute Constituency.
Last Date For Submission3rd Aug, 2026
Opening Date04 Aug, 2026
Cost
Document Cost5000.00
EMD41600.00
Estimated Cost2079628.00
Location
CityGoa
StateGoa

Register to see full details

BOQ Items
#ItemQtyUnits
1Earthwork in excavation by mechanical means in all types of strata comprising any of the materials such as soil, sand, ,silt clay,gravel,moorum of all varieties shingles,pebbles,all types of conglomarets ,laterite rock,soft rock, disintegrated or weathered rock, fissured shattered, decomposed rock, and such materials either in full or parts,as the case may be adopting any approved method or methods as may be convenient or permitted including chiseling,wedging etc. but blasting prohibited in all conditions such as dry, moist,saturated,submerged,foul conditions etc. including pumping or bailing out water/ dewatering including setting out constructed of shoring and bracing, removel of stump and other deleterious matter, dressing of sides and bottom and back filling the excavated earth to the extent required and disposal of excavated soil/rock at specified areas within a 50m lead and with all lifts etc. as per specification & drawing and directed by Engineer-in -Charge etc. complete.218.00Cum
2Rubble packing with hard laterite stone under floors including watering ramming and consolidating etc. in pipeline trenches and other foundations complete.16.00Cum
3Centering and shuttering including strutting, propping etc. and removal of formwork for : Foundations, footings, bases for columns and mass concrete.294.00Sq.m
4Providing & laying cement concrete 1:2:4 (1 cement: 2 coarse sand: 4 graded granitic or basaltic stone aggregate. 20 mm. nominal size) excluding cost of centering, shuttering and finishing in: All works upto plinth level211.00Cum
5Construction of embankment with approved material obtained from borrowpits with all lifts and leads, transporting tp site, spreading , grading to required slope and compacting with vibratory roller to meet requirement of Table 300-2 as per MORTH specification 305.175.00Cum
3rd Aug, 2026

6 Days Left

WhatsApp