Empowering Indian businesses in the procurement ecosystem since 2012
| Tender ID | 5023895 |
|---|---|
| Organisation Name | Rural Works Department |
| Tender Brief | Aruha To Taranjia_road_pmc, Seal Coat _2.000 To 3.000 |
| Last Date For Submission | 27th Jul, 2026 |
| Opening Date | 28 Jul, 2026 |
| Document Cost | 4000.00 |
|---|---|
| EMD | 9230.00 |
| Estimated Cost | 922678.00 |
| City | Jajpur |
|---|---|
| State | Odisha |
| # | Item | Qty | Units |
|---|---|---|---|
| 1 | Clearing and grubbing the road land including uprooting Rank vegetation grass bushes shrubs etc complete and as per direction of Engineer-in-Charge. | 974.600 | sqm |
| 2 | Labour for scraping cleaning the road for laying built up spray grout in one layers 37.5 mm thick applying tack coat using 3 kg of bitumen , 0.45 cum of 25 mm to 40 mm size h.g metal and 12 kg of penetration grade bitumen for10 sqm.in each layer with 0.12 cum of 12 mm size h.g.chips as key stones spreading and laying including heating pouring bitumen metal and chips and rolling with PRR with all labour T & P etc. complete. as per direction of Engineer-in-Charge. AR-2006, P-152, SL-28 | 584.003 | sqm |
| 3 | Providing and applying Tack Coat with penetration grade of bitumen emulsion including all cost, carriage, royality, taxes of materials etc. complete as per direction of Engineer-in-Charge. (Mannually) | 1,661.250 | sqm |
| 4 | Providing and laying 20 mm thick Premix Carpet using 0.18 cum of 13.2 mm and 0.09 cum of 11.2 mm size chips with 14.60 kg. penetration grade of bitumen per 10 sqm including hand packing to proper camber and rolling with PRR including hire and running charges of PRR, tar boiler and other T&P articles including all cost, carriage, royality of chips and bitumen etc. (With H.M.plant) AR-147,SL-21 | 1,661.250 | sqm |
| 5 | Providing and laying 6 mm thick precoated Seal Coat Type - B using 0.06 cum of 6.7 mm size chips and down graded as per sieve analysis and 6.8 kg. of bitumen per 10 sqm including hire and running charges of PRR, bitumen mixture, tar boiler etc including all cost, carriage, royality of chips and bitumen etc.(With H.M.plant) | 1,661.250 | sqm |
6 Days Left