Empowering Indian businesses in the procurement ecosystem since 2012
| Tender ID | 5908750 |
|---|---|
| Organisation Name | Public Works Department |
| Tender Brief | Construction Of Buldega Main Road To Bhinjpur Approach Road Via Sukhasupara Road Length 2.50 Km. Distt Jashpur |
| Last Date For Submission | 21st Oct, 2026 |
| Opening Date | 26 Oct, 2026 |
| Document Cost | 0.00 |
|---|---|
| EMD | 145215.00 |
| Estimated Cost | 19362000.00 |
| City | Jashpur |
|---|---|
| State | Chhattisgarh |
| # | Item | Qty | Units |
|---|---|---|---|
| 1 | Clearing and grubbing road land including uprooting rank vegetation, grass, bushes, shrubs, saplings and trees girth up to 300 mm, removal of stumps of trees cut earlier and disposal of unserviceable materials and stacking of serviceable material to be used or auctioned including all leads and lifts removal and disposal of top organic soil not exceeding 150 mm in thickness if required and as per relevant clauses of section-200. In area of light jungle | 03.45 | hectare |
| 2 | Excavation in Soil (by Mechanical Means.)Excavation for roadway in soil using mechanical means including loading in tipper for carrying of cut earth to embankment site and unloading with all leads & lifts as per relevant clauses of section 300. | 1,916.69 | cum |
| 3 | Construction of Embankment/sub-grade with Material Deposited from Roadway Cutting Construction of embankment/sub-grade with approved materials having required C.B.R. for embankment/sub-grade (unless specified otherwise in the contract) deposited at site from roadway cutting and excavation from drain and foundation of other structures graded and compacted to meet requirement of table 300-2. | 1,341.68 | cum |
| 4 | Construction of embankment with Material Obtained from Borrow Pits/Borrow Area (Construction of embankment with approved material/selected soil having C.B.R.>5 (unless specified otherwise in the contract) obtained from borrow pits with all lifts and leads, transporting to site, spreading, grading to required slope and compacting to meet requirement of table 300-2) | 14,357.54 | cum |
| 5 | Granular Sub-base as per Table:- 400-1Construction of granular sub-base by providing graded Material, , carriage of mixed Material to work site, spreading in uniform layers with motor grader on prepared surface watering, rolling and compacting with vibratory power roller at OMC to achieve the desired density, complete as per clause 401 Plant mix method (with Mechanically crushed stone only)(b) For Lower Sub-base with (i) Grading-V Material | 2,336.00 | cum |
18 Days Left