Empowering Indian businesses in the procurement ecosystem since 2012
| Tender ID | 4447081 |
|---|---|
| Organisation Name | Public Works Department |
| Tender Brief | Kalpetta Bypass Upgradation To Four Lane With Paved Shoulder - Work For Alignment / Boundary Stone Of Kalpetta Bypass From Km. 70/500 To 75/000 Of Nh 766 In Epc Mode In The State Of Kerala Under Annual Plan 2025-26-general Civil Work |
| Last Date For Submission | 3rd Jun, 2026 |
| Opening Date | 05 Jun, 2026 |
| Document Cost | 1060.00 |
|---|---|
| EMD | 11987.00 |
| Estimated Cost | 479487.00 |
| City | Koduvally |
|---|---|
| State | Kerala |
| # | Item | Qty | Units |
|---|---|---|---|
| 1 | Appendix A-Surveying , Boundary stone laying, Junction Design , Land Acquisition plan, Traffic survey and Topographic Survey | ||
| 2 | OD284201/2025-2026:Imposing the Field Measurement Books on alignment drawing, preparing LA strip plan with the list of survey numbers, tabulation of LA particulars including buildings and extends of each plot to be acquired as per direction of the Engineer in Charge including all cost of transportation, labour, preparing drawings with sufficient copies, collecting data etc complete. (for a width of 10m) | 3.800 | km |
| 3 | OD284199/2025-2026:Setting up GTS points (customized concrete pillar) on the project road with respect to known elevation of Pattambi railway station as per the direction of Engineer in Charge including all cost of labour, materials, transportation, collecting data, hire charge of equipment, painting and marking, indicating same in alignment drawing etc complete | 2.000 | each |
| 4 | 8.16:Reinforced cement concrete M-15 grade boundary pillars of standard design as per IRC:25-19767, fixed in position including finishing and lettering but excluding painting . | 298.000 | no |
| 5 | OD284202/2025-2026:Total Station Surveying for taking detailing in heavily built up area or in roads with heavy traffic or in thick vegetation for taking ID points of roads centre, road edges, kerbs, drain, compound wall, electric post, trees, CD works, RoW, Gail pipeline bounndary ,Buildings Monuments,Religious structures at an average of 1 per 1Om2 etc for a land width as specified including providing necessary road flags, temporary barricade and caution board etc including all necessary traffic safety measures and processing, preparation of drawings in AUTOCAD with various details in different layers and submission of finished drawings with x, y, z coordinates ensuring all objects, break lines and spot levels, topographic survey data for creation of DTM of the surveyed corridor compactible with road design softwares like MX ROAD, AUTOCAD CIVIL 3D, submission of detailed survey data in MS EXCEL. dxf, .sdr format - and all other relevant data in hard copy and soft copy and as directed by the engineer at site. | 3.040 | Hectare |