Empowering Indian businesses in the procurement ecosystem since 2012
| Tender ID | 4305455 |
|---|---|
| Organisation Name | Urban Improvement Trust |
| Tender Brief | Corrigendum : Construction Of Singhdwar At Jhalawar Road Gopalpura, Kota |
| Last Date For Submission | 1st Jun, 2026 |
| Opening Date | 02 Jun, 2026 |
| Document Cost | 2500.00 |
|---|---|
| EMD | 96200.00 |
| Estimated Cost | 4810000.00 |
| City | Kota |
|---|---|
| State | Rajasthan |
| # | Item | Qty | Units |
|---|---|---|---|
| 1 | Earth work in excavation by mechanical means (Hydraulic excavator )/ manual means over areas (exceeding 30cm in depth. 1.5m in width as well as 10 sqm on plan) including disposal of excavated earth, lead upto 50m and lift upto 1.5 m , disposed earth to be levelled and neatly dressed : All kinds of soil | 186.00 | Cum |
| 2 | Filling available excavated earth (excluding rock) in trenches, plinth side of foundation etc. in layers not exceeding 20 cm. in depth, consolidating each deposited layer by ramming and watering including lead up to 50 meter and with all lift. | 186.00 | Cum |
| 3 | Providing and laying in position cement concrete including curing, compaction etc. complete in specified grade excluding the cost of centering and shuttering - All work up to plinth level. M10 grade Nominal Mix 1: 3: 6 (1 cement : 3 coarse sand : 6 graded stone aggregate 20mm nominal size). | 33.00 | Cum |
| 4 | Providing and laying in position Ready mix concrete manufactured in fully automatic Batching Plant and transported to site in transit mixer for having continous agitated mixer, manufactured as per approved mix design of specified grade of RCC work including pumping of R.M.C. from transit mixer to site of laying , exculding the cost of centering, shuttering and reinforcement with all lead and lift including cost of admixtures in recommended portion as per IS 9103 to accelerate/ retard setting of concrete, improve workability without impairing strength and durability as per direction of Engineer in charge. All works upto floor V floor M20 grade Design Mix by using cement as per codal provision. | 84.00 | Cum |
| 5 | Add extra for providing richer mixes respectively at all floor levels Providing M-25 grade concrete by using cement as per codal provision instead of M-20 grade design mix. | 84.00 | Cum |
5 Days Left