Empowering Indian businesses in the procurement ecosystem since 2012
| Tender ID | 3641905 |
|---|---|
| Organisation Name | Energy And Petrochemicals Department |
| Tender Brief | Corrigendum : Providing And Fixing Barbed Wire Fencing At Lhp Area And Other Locations At Kltps. |
| Last Date For Submission | 18th Apr, 2026 |
| Opening Date | Refer to Documents |
| Document Cost | 1770.00 |
|---|---|
| EMD | 60912.00 |
| Estimated Cost | 0.00 |
| City | Kutch |
|---|---|
| State | Gujarat |
| # | Item | Qty | Units |
|---|---|---|---|
| 1 | Excavation for foundation up to 1.5m depth including sorting out and stacking of useful materials & disposing off the excavated stuff up to 50m lead (A) Loose or soft soil | 183.00 | CUM |
| 2 | Providing and laying cement concrete work 1:2:4 (1-Cement : 2- Coarse sand : 4- graded stone aggregates 20 mm nominal size) and curing complete excluding cost of formwork and reinforcement for reinforced concrete work in (A) Foundation and plinth | 188.00 | CUM |
| 3 | Providing formwork of ordinary timber planking so as to give a rough finish including centering shuttering strutting and propping etc. Height of propping and centering below supporting floor to ceiling not exceeding 4 M. and removal of the same for in situ reinforced concrete and plain concrete work in (A) Foundations footings bases of columns etc. and mass concrete. | 1625.00 | SQM |
| 4 | Providing and fixing pre-cast RCC post for fencing. All RCC pre-cast post will be prepared of size 0.10 mtr x 0.10 mtr and 1.50 mtr height in good quality of M200 concrete with required reinforcement as design/directive by EIC and as per requirement of GSECL. The work also including cost of all materials like cement, sand, metal, water with all tools & tackles, labours, curing etc complete. The rate is including all transportation, loading, unloading and fixing in line and level directed by EIC. (All the materials to be brought by contractor at his own cost) | 2000.00 | No |
| 5 | Providing and fixing four horizontal lines and two diagonals of galvanized steel barbed wire weighting 9.38 kg per 100 meter, strained and fixed to posts with GI staples including cost of tools and tackles, labour work etc. | 5000.00 | RMT |
11 Days Left