| Tender ID | 4318384 |
|---|---|
| Organisation Name | Rural Engineering Department |
| Tender Brief | Corrigendum : Under District Lucknow, Construction Of Women Hostel And Boundary Wall On The Available Land In The Garden Of Udyan Bhavan, Lot No 1 |
| Last Date For Submission | 6th Jun, 2026 |
| Opening Date | 06 Jun, 2026 |
| Document Cost | 5000.00 |
|---|---|
| EMD | 716000.00 |
| Estimated Cost | 35782000.00 |
| City | Lucknow |
|---|---|
| State | Uttar Pradesh |
| # | Item | Qty | Units |
|---|---|---|---|
| 1 | Work | ||
| 2 | Excavation in foundations in ordinary soil (Loam clay or sand) including lift upto 1.5 m (5 fts.) and lead upto 30 mt. (100 fts.) & including filling, watering and ramming of excavated earth into the trenches or into the space between the building and the sides of foundation trenches or into the plinth and removal and disposal of surplus earth as directed by the Engineer-Incharges upto a distance of 30mt. (100 fts) from the foundation trenches DEPTH FROM 0.00 TO 1.50 MTR..DSR 2.8.1 | 478.980 | CUM |
| 3 | Excavation in foundations in ordinary soil (Loam clay or sand) including lift upto 1.5 m (5 fts.) and lead upto 30 mt. (100 fts.) & including filling, watering and ramming of excavated earth into the trenches or into the space between the building and the sides of foundation trenches or into the plinth and removal and disposal of surplus earth as directed by the Engineer-Incharges upto a distance of 30mt. (100 fts) from the foundation trenches. DEPTH FROM 1.50 TO 1.825 MTR.DSR 2.8.1+2.26 | 80.860 | CUM |
| 4 | Filling available excavated earth (excluding rock) in trenches, plinth, sides of foundations etc. in layers not exceeding 20cm in depth, consolidating each deposited layer by ramming and watering, lead up to 50 and for all lift.DSR 2.25 | 87.860 | CUM |
| 5 | Providing and laying cement concrete 1:4:8 (1 cement :4 coarse sand :8 graded Stone aggregate 40 mm nominal size) including supply of all materials, labour T & P rtc required for proper completion of the work and curing complete also including cost of formwork in foundation & floors. DSR 4.1.8 | 55.340 | CUM |