Tender BriefCorrigendum : Ward No. 15 Jagatapuri Me Fire Station Ke Peeche Nagar Palika Tubewell Ke Room Ka Nirman Kary.
Last Date For Submission25th Apr, 2026
Opening Date25 Apr, 2026
Cost
Document Cost590.00
EMD48700.00
Estimated Cost486500.00
Location
CityModinagar
StateUttar Pradesh

Register to see full details

BOQ Items
#ItemQtyUnits
1Excavation in foundation in ordinary soil (Loam clay or sand ) including lift upto 1.50M and lead upto 30M, and including filling watering and ramming of excavated earth into the trenches or into the space between the building and the sides of foundation trenches or into the plinth and removal and disposal of surplus earth as directed by the Engineer-in-incharge upto ta distance of 30M from the foundation trenches. S.I.No. 251(a)11.49cum
2Concrete with 4 cm. guage stone ballast, Fine sand of 1.25 F.M. and cement, in proportion of 12:6:1 in foundation and under floors including supply of all materials, labour Tools & plants etc.required for proper completion of the work.1.83cum
3Providing and injecting chemical for preconstructional antitermite treatment and creating and chemical barrier under and around the column pits wall trenches basement excavation top surface in plinth filling juction of wall and floor, along the external per meter of binding expansion joints surrounding of pipes and conduit etc. complete (plinth area of the building at ground floor only shall be measured as per I.S. 6313 (part ll 1981) Aldrine emulsifiable concentrate or any other approved material such as Hepthachlor of chlordance of chemical emulsion shall be as follows :- Treatment of surface of plinth filling 5 liters per sqm13.86Sqm
4M-150 Brick work in one cement and four corse sand (1:4 ) in foundation and plinth including supply of all materials labour, T&Petc. Reqd. For proper completion of the work16.29cum
5M-150 Brick work in one cement and four corse sand (1:4 ) in superstructure including necessary cutting & moulding of brick including supply of all materials labour, T&P etc. Reqd. for proper completion of the work.8.32cum