Empowering Indian businesses in the procurement ecosystem since 2012
| Tender ID | 4579082 |
|---|---|
| Organisation Name | Directorate Of Urban Local Bodies |
| Tender Brief | Corrigendum : Construction Of A 5 Seater Urinal (3 For Men And 2 For Women) On King Road, Municipal Council, Hamirpur. |
| Last Date For Submission | 6th Jul, 2026 |
| Opening Date | 07 Jul, 2026 |
| Document Cost | 650.00 |
|---|---|
| EMD | 28000.00 |
| Estimated Cost | 0.00 |
| City | Multi city |
|---|---|
| State | Uttar Pradesh |
| # | Item | Qty | Units |
|---|---|---|---|
| 1 | Boring of 30cm dia piles of single under reamed of 50cm dia of bulb and 5 meter depth in black cotton soil with hand operated auger machine including all laboure T&P etc. for proper completion of work as per IS code-2911(Part-III) 1980. | 3.00 | No. |
| 2 | Excavation in foundation in ordinary soil ( Loam clay or sand) including lift up to 1.5 meter (5ft) and lead upto 30m (100ft) and including filling,watering & ramming of excavated earth into the trenches or into the space between the building and the sides of foundation trenches or into the plinth and removal and disposal of surplus earth as direction by the Engineer-in-charge upto a distance of 30m(100ft) from the foundation trenches. | 4.14 | Cum |
| 3 | Supplying and filling in plinth with sand under floors, including watering,ramming, consolidating and dressing complete.As per DSR-2.27 | 1.03 | Cum |
| 4 | Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level :1:4:8 (1 Cement : 4 coarse sand (zone-III) derived from natural sources : 8 graded stone aggregate 40 mm nominal size derived from natural sources).As per DSR-4.1.8 | 1.03 | Cum |
| 5 | Reinforced cement concrete work in walls (any thickness), including attached pilasters, buttresses, plinth and string courses, fillets, columns, pillars, piers, abutments, posts and struts etc. above plinth level up to floor five level, excluding cost of centering, shuttering, finishing and reinforcement 1:1.5:3 (1 cement : 1.5 coarse sand(zone-III) : 3 graded stone aggregate 20 mm nominal size) :.As per DSR-5.2.2 | 3.20 | Cum |
5 Days Left