Complete Tender Details

Empowering Indian businesses in the procurement ecosystem since 2012

Tendering Authority: Public Works Department
Tender ID4908782
Organisation NamePublic Works Department
Tender BriefCorrigendum : Construction Of A Community Building At The Government Degree College In Rabupura Gautam Buddha Nagar District Under The Accelerated Economic Development Scheme For The Financial Year 2025-26
Last Date For Submission20th Jul, 2026
Opening Date20 Jul, 2026
Cost
Document Cost944.00
EMD170000.00
Estimated Cost1689647.00
Location
CityMulti city
StateUttar Pradesh

Register to see full details

BOQ Items
#ItemQtyUnits
1Clearing jungle including up rooting of trunk vegetation grass bush wood trees and sapling of girth upto 30cm. Measured at a height of 1 meter above ground level and removal of rubbish upto a distance of 50m. outside the periphery of area clearedIncluding cost of, all material, labour, T&P, Labour cess, all taxes complete. But excluding GST. DSR SI.No. 2.3178.00Sqm
2Earth work in excavation by mechanical means (Hydraulic excavator) / manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms, for all lift, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m. All kinds of soil.Including cost of, all material, labour, T&P, Labour cess, all taxes complete. But excluding GST. DSR SI.No. 2.8.120.00Cum
3Diluting and injecting chemical emulsion for POST-CONSTRUCTIONAL anti-termite treatment (excluding the cost of chemical emulsion) Treatment of soil under existing floors using chemical emulsion @ one litre per hole, 300 mm apart including drilling 12 mm diameter holes and plugging with cement mortar 1 :2 (1 cement : 2 Coarse sand) to match the existing floor: With Chlorpyriphos/Lindane E.C. 20% with 1% concentration Including cost of, all material, labour, T&P, Labour cess, all taxes complete. But excluding GST. DSR SI.No. 2.35.3.178.00Sqm
4Supplying and filling in plinth with river sand under floors including, watering, ramming consolidating and dressing complete. Including cost of, all material, labour, T&P, Labour cess, all taxes complete. But excluding GST. DSR No. 2.275.00Cum
5Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level : 1:4:8 (1 Cement : 4 coarse sand (zone-lll) derived from natural sources : 8 graded stone aggregate 40 mm nominal size derived from natural sources) Including cost of, all material, labour, T&P, Labour cess, all taxes complete. But excluding GST.DSR SI no. 4.1.814.00Cum