Complete Tender Details

Empowering Indian businesses in the procurement ecosystem since 2012

Tendering Authority: New Okhla Industrial Development Authority
Tender ID4450639
Organisation NameNew Okhla Industrial Development Authority
Tender BriefDevelopment Of Sector-117( Raising And Fencing Of Boundary Wall Of Green Belt In Sector-117), Noida
Last Date For Submission4th Jun, 2026
Opening Date05 Jun, 2026
Cost
Document Cost2124.00
EMD99000.00
Estimated Cost4153213.00
Location
CityNoida
StateUttar Pradesh

Register to see full details

BOQ Items
#ItemQtyUnits
1Demolishing R.C.C. work manually/ by mechanical means including stacking of steel bars and disposal of unserviceable material within 50 metres lead as per direction of Engineer - in- charge3.50Cum
2Reinforced cement concrete work in beams, suspended floors, roofs having slope up to 15 landings, balconies, shelves, chajjas, lintels, bands, plain window sills, staircases and spiral stair cases above plinth level up to floor five level, excluding the cost of centering, shuttering, finishing and reinforcement with 1:1.5:3 (1 cement : 1.5 coarse sand(zone-III) : 3 graded stone aggregate 20 mm nominal size).119.50Cum
3Centering and shuttering including strutting, propping etc. and removal of form for : Lintels, beams, plinth beams, girders, bressumers and cantilevers1037.00Sqm
4Steel reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding all complete upto plinth level. Thermo-Mechanically Treated bars of grade Fe-500D or more14495.00Kg
5Washed stone grit plaster on exterior walls height upto 10 metre above ground level, in two layers, under layer 12 mm cement plaster 1:4 (1 cement : 4 coarse sand ), furrowing the under layer with scratching tool, applying cement slurry on the under layer @ 2 Kg of cement per square metre, top layer 15 mm cement plaster 1:1/ 2:2 (1 cement: 1/2 coarse sand : 2 stone chipping 10 mm nominal size), in panels with groove all around as per approved pattern, including scrubbing and washing the top layer with brushes and water to expose the stone chippings ,complete as per specification and direction of Engineer-in-charge (payment for providing grooves shall be made separately).1852.00Sqm