| Tender ID | 4651549 |
|---|---|
| Organisation Name | Military Engineer Services |
| Tender Brief | Corrigendum : Special Repairs To Building No P-291 (diesel Wing) At Ins Shivaji Lonavla |
| Last Date For Submission | 17th Jul, 2026 |
| Opening Date | 20 Jul, 2026 |
| Document Cost | 1000.00 |
|---|---|
| EMD | 291000.00 |
| Estimated Cost | 14521000.00 |
| City | Pune |
|---|---|
| State | Maharashtra |
| # | Item | Qty | Units |
|---|---|---|---|
| 1 | Dismantling of floor, hearth or wall tiling including cement mortar bedding complete all as specified and directed. | 174.40 | Sqm |
| 2 | Material and labour for Non skid ceramic coloured tiles 7 to 8 mm thick (square/rectangular) area of each tiles exceeding 0.06 sqm but nexc 0.11 sqm in floors etc set and jointed in neat cement slurry and pointed in white or coloured cement to match etc over and including screed bed or bedding layer 20 mm thick in cement mortar 1:6 for laying tiles complete all as specified. ( Note: screed bed shall also deemed to be included in the quoted rate by the contractor.) | 35.50 | Sqm |
| 3 | Material and labour glazed ceramic coloured tiles, 450x350 x7mm thick, in dado/skirting and vertical surfaces set and jointed in neat cement slurry and pointed in white cement to match including rendering 10 mm thick in cement mortar 1:4 for laying tiles complete all as specified. ( Note: screed bed shall also deemed to be included in the quoted rate by the contractor.) | 138.90 | Sqm |
| 4 | Surface Preparation: All loose and de-bonded concrete/ screed, loose particles, dirt & APP membrane treatment should be removed. Roof substrates must be pressure-washed with water with a minimum working pressure of 1,400 psi to be used to and/or remove all dirt, dust, chalking and waste products. Remove algae, mold by using bleach solution or biowash. | 314.90 | Sqm |
| 5 | Screed Repair:Mechanical cutter is used to Remove loose and damaged concrete roof screed in pockets . Clean the concrete screed with high pressure water jet to remove dirt and loose particles. Brush applies a bond coat of Dr. Fixit Pidicrete SBR mix in the ratio of 1:1 (URP 1: Cement 1) by volume to make it lump free slurry when applied on in the pre wet surface. Laid to fall roof screed in correct slope and gradient. Mix Dr. Fixit Pidicrete URP 10% by weight of cement in (M20) concrete in ratio of 1:1.5:3 i.e., one bag of 50kg cements: 1.5 times volume of sand: 3 times volume of aggregates: 25L water. Level the repair mortar and finish with trowel. Moist cure should be done for 7days. Air cure screed for 4-5 days, before application of roof topcoat coating system. | 314.90 | Sqm |