Tender BriefTender For Rerouting Of Steel Pipeline (hot Tapping And Double Stopple Method) And Mdpe Pipeline At Mngl Pune Ga
Last Date For Submission20th Jul, 2026
Opening Date21 Jul, 2026
Cost
Document Cost0.00
EMD200000.00
Estimated Cost0.00
Location
CityPune
StateMaharashtra

Register to see full details

BOQ Items
#ItemQtyUnits
1Re-routing of UG Steel Pipeline The SOR covers re-routing of steel pipe line by Transportation of Pipe, loading, unloading of the line pipes to the site, (Excluding Trench) laying of pipeline with dewatering and cleaning of pit or trench if required, Welding, NDT, DPT, joint coating, holiday testing, backfilling, laying of warning mat, hydrotesting, pigging, swabbing of pipes, N2 purging etc. which required to complete the pipeline mechanically and commissioning of pipeline as per approval by EIC. Surface and bevel preparation, DP checking, Drying of the section if required etc. and as per requirement at site and direction given by EIC. Contractor to carry out all the activities involved in Pre- commissioning and commissioning and ensure the safety requirements such as PPEs, barricading, sign boards, blinking light etc. to complete the section work in day and night as directed by EIC. Contractor to arrange all necessary equipment, DG, pipe line fittings, consumables, manpower with PPE's, Fire extinguishers, Fire fighting services and local coordination as required etc. to complete the job. After Completion of the job all related documents to be submitted. Job shall be carried out as per ASME B 31.8/ API 1104 in all aspect as per the satisfaction of MNGL.
2Tenching for 10'' & 4'' steel pipeline laying at rocky terrain area at 1.2 Meter top cover700.00Meter
34'' Dia Re-routing/Laying UG PIPELINE130.00Meter
410'' Dia Re-routing/Laying UG PIPELINE700.00Meter
5Mobilization for Hook Up (UG Pipeline) The SOR covers additional manpower, site coordination,Liasioning, tools, equipments, machines, excavation, welding, NDT, Coating, backfilling, etc. whichever is required to complete the given hook up work in totality for all size of UG Pipeline. vendor can claim only 1 hook up qty per site/job/location. The SOR also covers, distribution of notice/ intimation letter to societies, police station, corporation, fire brigade etc. to execute the decommissioning and commissioning of the pipeline/ section including support for closing of both sides valves, venting the natural gas of the section, Nitrogen purging including supply, vaporizer, checking LEL etc. as per requirement at site and direction given by EIC. Contractor to carry out all the activities involved in De-commissioning and commissioning and ensure all safety requirements such as PPEs, barricading, sign boards, blinking light etc. to complete the section work in day and night as directed by EIC.