Complete Tender Details

Empowering Indian businesses in the procurement ecosystem since 2012

Tendering Authority: Forest Department
Tender ID4644294
Organisation NameForest Department
Tender BriefCorrigendum : Construction Of Second Floor Of Rapid Response Team Ranni Building In Ranni Range During The Year 2026-2027
Last Date For Submission1st Jul, 2026
Opening Date03 Jul, 2026
Cost
Document Cost2760.00
EMD45200.00
Estimated Cost1806848.00
Location
CityRANNI
StateKerala

Register to see full details

BOQ Items
#ItemQtyUnits
1Centering and shuttering including strutting, etc. and removal of form for:Suspendedfloors, roofs, landings, balconies and access platform161.030M2
2Steel reinforcement for R.C.C work including straightening, cutting, bending, placing in position and binding all complete upto plinth levelThermo - Mechanically Treated bars of grade Fe-500D or more3000.000kg
3Reinforced cement concrete work in walls (any thickness), including attached pilasters, buttresses, plinth and string courses, fillets, columns, pillars, piers, abutments, posts and struts etc. up tot floor five level excluding cost of centering, shuttering, finishing and reinforcement :1:1.5:3( 1 cement : 1.5 coarse sand : 3 graded stone aggregate 20 mm nominal size derived from natural sources)0.405M3
4Reinforced cement concrete work in beams, suspended floors, roofs, having slope upto 15 landings, balconies, shelves, chajjas, lintels, bands, plain window sills,staircases and spiral stair cases up to floor five level excluding the cost of centering,shuttering, finishing and reinforcement, with1:1.5:3 (1 cement : 1.5 coarse sand (Zone III) derived from natural sources: 3 graded stone aggregate 20 mm nominal size derived from natural sources).15.969M3
5Providing and laying Autoclaved Aerated concrete (AAC) blocks masonry 150mm/230mm/300 mm thick with Grade- I AAC blocks in super structure above plinth level up to floor V level with RCC band at sill level and lintel level with approved block laying polymer modified adhesive mortar all complete as per direction of Engineer-in-Charge. (The payment of RCC band and reinforcement shall be made for seperately)35.582M3
1st Jul, 2026

5 Days Left

WhatsApp