Empowering Indian businesses in the procurement ecosystem since 2012
| Tender ID | 3890215 |
|---|---|
| Organisation Name | Rural Development Department |
| Tender Brief | Construction Of Karad Panchayat Samiti Administrative Building Tal-karad Dist-satara |
| Last Date For Submission | 8th Apr, 2026 |
| Opening Date | 09 Apr, 2026 |
| Document Cost | 29500.00 |
|---|---|
| EMD | 1070000.00 |
| Estimated Cost | 1069974655.00 |
| City | Satara |
|---|---|
| State | Maharashtra |
| # | Item | Qty | Units |
|---|---|---|---|
| 1 | Excavation for foundation in earth, soil of all types, sand, gravel and soft murum, including removing the excavated material up to a distance of 50 metre beyond the building area and stacking and spreading as directed, dewatering, preparing the bed for the foundation and necessary back filling, ramming, watering including shoring and strutting excetra complete. - (Lift upto 1.5 metre) By Mechanical Means Item / Page No : 2 / 153 Specification No : Bd.A.1 Spec. Page No : 259 Additional Specifications : The useful excavated material shall be utilised as directed by the Engineer in-charge. | 690.1800 | Cubic Metre |
| 2 | Providing dry trap/ granite/ quartzite/ gneiss rubble stone soiling 15 centimetre to 20 centimetre thick including hand packing and compacting, excetra complete. Item / Page No : 38 / 157 Specification No : Bd.A.12 Spec. Page No : 264 | 409.5600 | Cubic Metre |
| 3 | Filling in plinth and floors with contractors material / brought from outside and approved by Engineer In-Charge, in 15 centimetre to 20 centimetre layers including watering and compaction, excetra complete. Item / Page No : 37 / 157 Specification No : Bd.A.11 Spec. Page No : 263-264 | 1258.7800 | Cubic Metre |
| 4 | Providing preconstructional antitermite treatment as per Indian Standard 6313 (Part-II) by treating the top surface of plinth filling at the rate of 5 litres of emulsion concentrate of 1.0 percent of clorophyriphoas per square metre of surface area covering ten years guarantee on bond paper. Item / Page No : 24 / 156 Additional Specifications : 1. The work shall be carried out as per instructions of Engineer in-charge. 2. The amount of 10 percent of the total cost of the completed item sahll be retained as retention money for the full guarantee period of ten years. 3. If the use of any chemical is found banned by the Government, proper substitute chemical will be allowed to be used as per manufactures code of practice. The chemical shall be got approved from Engineer in-charge. 4. The recoupment of the damages if any found and communicated to the contractor in writing is not made good within two weeks from the date of receipt of such communication by him, the same shall be carried out departmentally on his behalf and cost thereof shall be met with from sum withheld as aforesaid. In case the sum recoverable from the contractor is more than that of the sum of withheld amount, the difference shall stand recoverable as arrears of land revenue from the contractor under clause 20 of original contract. 5. The mode of measurement shall be on square metre basis. | 2266.2600 | Square Metre |
| 5 | Providing preconstructional antitermite treatment as per Indian Standard 6313 (Part-II) by treating the backfill in immidiate contact with foundation at the rate of 5 litres of emulsion concentrates of 1.0 percent of clorophyriphoas per square metre of vertical surface area covering ten years guarantee on bond paper. Item / Page No : 23 / 155 Additional Specifications : 1. The work shall be carried out as per instructions of Engineer in-charge. 2. The amount of 10 percent of the total cost of the completed item sahll be retained as retention money for the full guarantee period of ten years. 3. If the use of any chemical is found banned by the Government, proper substitute chemical will be allowed to be used as per manufactures code of practice. The chemical shall be got approved from Engineer in-charge. 4. The recoupment of the damages if any found and communicated to the contractor in writing is not made good within two weeks from the date of receipt of such communication by him, the same shall be carried out departmentally on his behalf and cost thereof shall be met with from sum withheld as aforesaid. In case the sum recoverable from the contractor is more than that of the sum of withheld amount, the difference shall stand recoverable as arrears of land revenue from the contractor under clause 20 of original contract. 5. The mode of measurement shall be on square metre basis. | 268.7500 | Square Metre |