| Tender ID | 5020854 |
|---|---|
| Organisation Name | Directorate Of Secondary Education |
| Tender Brief | Repair And Renovation Of Existing Toilet Blocks In Gopinagar Sb, Sukhomoybhumihin Col Jb,ujanpathaliaghatsb, Dwarkaikaipeng Jb, Ujanlarma Sb And Dulkaipara Jb Schools Under Jampuijala And Bishalgarh Blocks Of Sepahijala District Under Pm Special Sche |
| Last Date For Submission | 27th Jul, 2026 |
| Opening Date | 28 Jul, 2026 |
| Document Cost | 1000.00 |
|---|---|
| EMD | 31480.00 |
| Estimated Cost | 1574000.00 |
| City | Sepahijala |
|---|---|
| State | Tripura |
| # | Item | Qty | Units |
|---|---|---|---|
| 1 | Earth work in excavation by mechanical means (Hydraulic excavator) / manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan) including dressing of sides and ramming of bottoms, lift upto 1.5 m, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m. -All kinds of soil | 77.626 | cum |
| 2 | Filling available excavated earth (excluding rock) in trenches, plinth, sides of foundations etc. in layers not exceeding 20cm in depth, consolidating each deposited layer by ramming and watering, lead up to 50 m and lift upto 1.5 m. -All kinds of soil | 51.750 | cum |
| 3 | Supplying and filling in plinth, under floor, foundations etc. with sand (fine) from local quarry with all lifts including spreading in horizontal layers, watering, grading to required slope, ramming, consolidating and compacting each layer by using plate compactor or by any suitable method complete | 7.7630 | cum |
| 4 | Demolishing brick work including stacking of serviceable materials and disposal of unserviceable materials with all lifts and upto a lead of 50m etc. complete as per direction of the Engineer- in-charge:-In cement mortar. | 76.180 | cum |
| 5 | Demolishing cement concrete manually /by mechanical means including disposal of material with all lifts and upto 50 m lead etc. complete as per direction of the Engineer- in-charge:-Nominal concrete 1:3:6 or richer mix (i/c equivalent design mix) | 135.340 | cum |