Empowering Indian businesses in the procurement ecosystem since 2012
| Tender ID | 4261591 |
|---|---|
| Organisation Name | Uttar Pradesh Power Transmission Corporation Limited |
| Tender Brief | Corrigendum : Replacement Of Damaged Gaskets And Overhauling Oltc/diverter Switch Of 40mva T/f-ii (ngef Make, Mfg. Year 1998) Alongwith Other Associated Works At 132kv Sub Station Naugarh Under Etd-ii Basti H.q At Siddharthnagar |
| Last Date For Submission | 28th May, 2026 |
| Opening Date | 29 May, 2026 |
| Document Cost | 590.00 |
|---|---|
| EMD | 4000.00 |
| Estimated Cost | 0.00 |
| City | Siddharthnagar |
|---|---|
| State | Uttar Pradesh |
| # | Item | Qty | Units |
|---|---|---|---|
| 1 | The following works are carried out for Replacement of Gaskets of 40MVA T/F-II (NGEF make) alongwith other associated Works at 132KV Sub Station Naugarh, with all Cost of Men, Misc. Consumables, Crane / Hydra, Centrifuging Machine, Normal & Special T&Ps, etc. Required for Satisfactory Completion of the Job, as per Technical Specifications & Direction of the Supervising Engineer, as per Details below : | ||
| 2 | Carriage of 20/40 KL empty oil tank for the centrifuging of T/F oil where it is available within distance of 50 Km Approx. including carefully loading empty oil tank at 220KV Substation Bansi & unloading at 132KV Substation Naugarh. | 1 | Job |
| 3 | Removal of Jumpers of HV & LV side Bushings of the Transformer. The Scope of Work Involves Opening of Bolts & Nuts and Removal of Jumpers, Bushing Clamps etc. | 1 | Job |
| 4 | Complete Draining of the T/F Oil from the 40MVA Transformer - II (NGEF make) into Oil Tanker / Oil Drums and Stacking them at Proper Place. | 16590 | Lit. |
| 5 | Complete Dismantling of the 40MVA Transformer-II (NGEF make). The Scope of Work Involves Dismantling of HV / LV / Neutral Bushings, Turrets, Radiators, Conservator Tank, Explosion Vent Pipe, Buchholz Relay, Oil Pipe Lines, Flanges, Valves, Cooling Fans etc. along with Opening of associated Electrical Connections, Stacking of all the Dismantled Parts at Proper Place in the Switchyard including Proper Blanking of the Open Points before Replacement of Gaskets. | 1 | Job |
7 Days Left