Tender BriefCorrigendum : Constructing Of One Room School Building At Bhadgaon Budruk Maladwadi Z P Primary School Tal Kudal
Last Date For Submission4th Aug, 2026
Opening Date05 Aug, 2026
Cost
Document Cost500.00
EMD10000.00
Estimated Cost994312.00
Location
CitySindhudurg
StateMaharashtra

Register to see full details

BOQ Items
#ItemQtyUnits
1Item no 1)Excavation for foundation in earth, soil of all types, sand, gravel and soft murum, including removing the excavated material up to a distance of 50 m. beyond the building area and stacking and spreading as directed, dewatering, preparing the bed for the foundation and necessary back filling, ramming, watering including shoring and strutting etc. complete. (Lift upto 1.5 m.)24.85Cmt
2Item no 2)Excavation for foundation in Soft rock and old cement or lime masonry foundations including removing the excavated material upto a distance of 50 metres beyond the building area and stacking as directed, including dewatering, preparing the bed for the foundation and necessary back filling with available earth /murum, ramming, watering including shoring and strutting etc. complete (lift upto 1.5m)2.76Cmt
3Item no 3) Providing and laying Cast in situ/Ready Mix cement concrete in M-10 of trap/ granite/ quartzite/ gneiss metal for foundation and bedding including bailing out water, formwork, laying/pumping, compacting, roughening them if special finish is to be provided, finishing if required and curing complete, with fully automatic micro processor based PLC with SCADA enabled reversible Drum Type mixer/concrete Batch mix plant (Pan mixer) etc. complete. With natural sand/V.S.I. quality Artificial Sand 226/24.017.55Cmt
4Item no 4) Providing laterite stone masnory in cement mortar 1:6 in foundation & plinth including racking out joints where plastering is to be done watering & scaffolding complete. P/I 1 24/09/2018 4522.00 R.A.17.32Cmt
5Item no 5) Filling in plinth and floorswith approved excavatedmaterial in 15cm. to 20cm. layers including watering and compacting etc. complete.15.23Cmt