Complete Tender Details

Empowering Indian businesses in the procurement ecosystem since 2012

Tendering Authority: Himachal Pradesh Irrigation And Public Health Department
Tender ID3997655
Organisation NameHimachal Pradesh Irrigation And Public Health Department
Tender BriefSh Construction Of Rcc Storage Tank 30000 Ltr. Capacity At Village Sayari. Job No. 1
Last Date For Submission21st Apr, 2026
Opening Date21 Apr, 2026
Cost
Document Cost350.00
EMD7800.00
Estimated Cost389023.00
Location
CitySolan
StateHimachal Pradesh

Register to see full details

BOQ Items
#ItemQtyUnits
1Excavation in foundation trenches etc. upto all depths in all classification of earth work such as pick work, jumper work, saturated soil including bailing of pumping out water, blasting soft/ hard rock or chiseling soft/ hard where blasting is prohibited. In all lifts including trimming and dressing of sides, levelling of beds to correct grade including shoring, strutting, planking timbering and dewatering wherever required, stacking the useable and un-useable material/ soil separately and then returning the stacked soil in 15cm (fifteen centimeters) layers where required into plinths, sides of foundations etc. including consolidating of each deposited layer by ramming and watering and then desposing of all surplus excavated soil un- useable materials complete in all respect with in all leads & lifts as per direction of the Engineer-in-charge.15.599P/Cum
2Providing and laying cement concrete 1:3:6 (1cement:3approved sand:6app.graded stone aggregate 40mm nominal size) and curing complete excluding cost of form work in foundation and plinth including entire carriage of material upto all leads and lifts.2.753Cum
3Providing and laying cement concrete 1:1.5:3 (1cement:1.5approved sand:3approved graded stone aggregate 20mm nominal size) and curing complete excluding cost of form work and reinforcement for reinforced concrete work in:-
4Wall (any thickness but not less than 0.1m thickness) attached pillasters, buttresses plinth and string courses etc. from top to foundation level upto floor two level and as per the direction of Engineer-in-charge.including entire carriage of material upto all leads and lifts.7.351P/Cum
5Foundation and plinth including entire carriage of material upto all leads and lifts.3.690P/Cum
21st Apr, 2026

7 Days Left

WhatsApp