| 1 | Design, Construction, Supply, Erection, Testing, Commissioning of 4.5 MLD average flow with peak factor Main Pumping Station (MPS) and 4.5 MLD capacity Sewage Treatment Plant based on Sequential Batch Reactor (SBR) Technology along with Tertiary Treatment complete in all respect including Landscaping, all other contingent i.e. Civil, Electrical, Mechanical, Piping and Instrumentation work with PLC and SCADA arrangement for STP integrated with MPS at STP including Tertiary treatment, Entire infrastructure including construction of Staff quarter, Administrative building cum Laboratory with equipment and tools, Boundary wall and plants as per detail given in the bid document comprises of 900 mm dia incoming sewer lines to be connected with last Manhole prior to MPS, Main Receiving Chamber Bv Pass Channel. Inlet Chamber, Coarse Screen Chamber, Distribution Chamber, wet well sump suitable for 4.5 MLD average flow with peak factor including Providing and installing non clog sewage submersible pump sets each equipped with VFD and suitable LT panel boards, all safety devices. automatic capacitor bank and suitable size submersible cable from LT panel to pumps, K9 DI pipe of suitable dia at MPS including welding and screwing of flanges, ISl marked D.1. fittings, Knife gate valves non-return valves as per requirements even for bye-pass arrangements along with necessary Knife gate valves etc., Piping Gallery, Stilling Chamber, Fine Screen Chamber, Grit Chamber, SBR Basin, Sludge Thickener, Necessary piping work with the required DI D/F Resilient seated Sluice Valve and sluice Valve Chambers, Belt Filter Press including Belt Filter Press feed pump, Chlorine Contact Tank, Chlorinator room,Pressure Sand Filter and Activated Carbon filters, Providing and laying of RCC pipe cater 4.5 MLD flow with peak factor as per CPHEEO manual from plant outlet to disposal point (Existing Nalla, named as Drain no. 6) for Disposal of Treated effluent of 4.5 MLD, complete in all respects as per complete scope of work mentioned in Annexure-l including 6 Years Defect Liability-cum-Maintenance Period (after 3 Months trial run) at Devru, Sonipat town.
(a) Entire Civil works, mechanical, electric and instrumentation works as per DNIT (As per detail attached at annexure- A and inclusive of O and M).
Detail of components are attached as annexure A1
Unit: 01 Job Brake up of cost for payment plan:-
Capital work 80%
DLP-cum-maintenance period 20% Scheduled of payment for DLP-cum-maintenance period is attached with DNIT
O and M includes all the scope of work included in the DNIT Payment scheduled is attached as annexure A2
Main-Component: Civil works/ Process Unit
Main Pumping Station
Stilling Chamber
Fine Screen Chamber
Grit Chamber
SBR Basin
Chlorination Disinfection Tank
Belt filter feed sump
Polyelectrolyte Dosing Tank
Main-Component: Civil Works/ Building Works
Chlorination cum Chlorine Tonner House
MCC and SCADA Building
Centrifugal Building
Centrifugal Feed Pump House (Sludge Pump and Blower House)
SBR Air Blowe
Admin Building
HT Substation
DG Room
Thickened Sludge Storage Shed
Guard Room
Store room
Staff Quarters
Boundary Wall
Electrical Works
Electric Estimate STP
Main-Component: Mechanical Works
Main Pumping Station
Inlet Chamber and fine Screen Chamber at STP
Grit Chamber at STP
SBR Basin at STP
Chlorination Disinfection
Sludge Thickener
Belt Filter Press
Pressure Sand Filter
Main-Component: Instrumentation Works
Instrumentation Works
Main-Component: 6 years defect liabilitv-cum-maintenance period 6 years defect liability-cum-maintenance period. | $1.000 | Job |