Empowering Indian businesses in the procurement ecosystem since 2012
| Tender ID | 4258248 |
|---|---|
| Organisation Name | Rural Development Department |
| Tender Brief | Corrigendum : Construction Of Ri Office Cum Residence Building At Hemgir_building |
| Last Date For Submission | 26th May, 2026 |
| Opening Date | 28 May, 2026 |
| Document Cost | 10000.00 |
|---|---|
| EMD | 74520.00 |
| Estimated Cost | 7451982.00 |
| City | Sundergarh |
|---|---|
| State | Odisha |
| # | Item | Qty | Units |
|---|---|---|---|
| 1 | Earth work excavation of foundation in hard soil with all leads and lifts including dressing the sides and levelling the bed of foundation including cost of all labour required for the work etc complete with all other T&P required for the work and stacking the excavated materials away from working area as directed by the Engineer-in-charge including 1% cess. Ground Floor | 111.531 | cum |
| 2 | Earth work excavation of foundation in hard soil with all leads and lifts including dressing the sides and levelling the bed of foundation including cost of all labour required for the work etc complete with all other T&P required for the work and stacking the excavated materials away from working area as directed by the Engineer-in-charge including 1% cess. Boundary wall | 229.500 | cum |
| 3 | Earth work excavation of foundation in hard soil with all leads and lifts including dressing the sides and levelling the bed of foundation including cost of all labour required for the work etc complete with all other T&P required for the work and stacking the excavated materials away from working area as directed by the Engineer-in-charge including 1% cess. Concrete road | 17.100 | cum |
| 4 | Earth work excavation of foundation in hard soil with all leads and lifts including dressing the sides and levelling the bed of foundation including cost of all labour required for the work etc complete with all other T&P required for the work and stacking the excavated materials away from working area as directed by the Engineer-in-charge including 1% cess. Concrete drain | 9.600 | cum |
| 5 | Supplying and filling in foundation and plinth with sand well watered & rammed with cost ,conveyance, royality & taxes of all materials and labour required for the work as per specification and including 1% cess as per direction of the Engineer-in-Charge. Ground Floor | 62.234 | cum |